Washington Hospital Health Care System
Fremont, California


Valued at $ 115 million his project includes a new 3 story 39,000 sf Center for Joint Replacement containing 27 Patient Rooms that provide pre- and post operative surgery services, a new 2 story 38,000 sf Central Plant with offices on 2nd floor & laundry facility on 1st floor, and a new interim loading dock facility with service tunnel that connects the dock to the new Central Plant and the Existing Hospital. The first Phase is schedule to be completed in 2011. As part of their pre-construction services Swinerton Contractors coordinated project with FCA in BIM. This helped to streamline the construction schedule and allowed for better coordination of building systems.
Completion Year: 2011

Charles King was the Project Manager and Construction Administrator for this project while employed by Fong & Chan Architects